Construction Arbitration — Issue 96

Pre-award interest barred by contract; post-award interest distinct

Clause specifically prohibiting payment of interest - whether claims adjudicated for delayed payments under the contract, such as, final bill, price variation clause amounts, and withheld dues, fell within the contractual prohibition - award of pre-award/pendente lite interest, by way of compensation - clause in the General Conditions of Contract (GCC) expressly prohibiting award of interest - granting post-award interest is not subject to the contract between the parties - pre-award and post-award interest operate in distinct fields and a contractual bar applicable to the former cannot, by implication, be extended to the latter, and thus, any exclusion of post-award interest must be explicit and unambiguous.

Union of India v. Larsen & Tubro Limited (L&T)

Conditional grant of post-award interest at 12% per annum

Conditional grant of post-award interest - rate of post-award interest at 12% per annum - absence of any justification in the award for fixing the rate at 12% per annum - such rate would result in an excessive financial burden and would not subserve the principle of just compensation.

Union of India v. Larsen & Tubro Limited (L&T)

Force majeure and site disturbances

Condition of force majeure - site disturbances whether fall within the meaning of “hostilities” and acts of “public enmity” - refusal of the Contractor to start the work whether amounts to abandonment of work - action of nuisance, threats and disruption of work was not by enmity but motivated simply to scare away the Contractor so that no construction could take place - land was handed over to the Contractor free of all encumbrances for starting the work and when the disturbance took place the Employer was fully involved in getting it removed - the interpretation given by the arbitral tribunal to the force majeure clause was not perverse.

Ramasethu Infrastructure v. Indian Railway Welfare Organisation
Union of India v. Larsen & Tubro Limited (L&T)
Supreme Court — Decided on 27.2.2026

The contract stipulated execution of work relating to the modernization of the Jhansi Workshop of North Central Railway. The original date for completion of the work was extended by the Employer on ten occasions, resulting in a total delay of 40 months beyond the original completion date. During this period, disputes concerning execution of the work and outstanding payments arose between the parties. The arbitral tribunal allowed some of the claims of the Contractor along with pre-award/pendente lite interest. The General Conditions of Contract (GCC) contained a clause providing that, “where the arbitral award is for payment of money, no interest shall be payable on the whole or any part of the money for any period till the date on which the award is made.”

The provisions contained in Section 31(7)(a) of the Arbitration and Conciliation Act give paramount importance to the contract entered into between the parties and categorically restrict the power of an arbitrator to award pre-award/pendente lite interest where the parties have themselves agreed to the contrary. The Court concluded that Clause 64(5) of the GCC barred interest only “till the date on which the award is made” and did not prohibit interest for the period subsequent thereto. Accordingly, the arbitral tribunal erred in awarding pre-award/pendente lite interest. However, there is no provision in the GCC which expressly bars the grant of post-award interest. Pre-award and post-award interest operate in distinct fields, and a contractual bar applicable to the former cannot, by implication, be extended to the latter. Therefore, any exclusion of post-award interest must be explicit and unambiguous.

The Court also considered the conditional grant of post-award interest at 12% per annum. In the absence of any justification in the award for fixing the rate at 12% per annum, such rate would result in an excessive financial burden and would not subserve the principle of just compensation.

Ramasethu Infrastructure v. Indian Railway Welfare Organisation
Delhi High Court — Decided on 24.3.2026

The disputes between the parties arose under a contract for construction of 140 dwelling units. Immediately after commencement of the tendered work, the local residents started raising objections and obstructing the work at the project site. The Contractor expressed its inability to continue the work due to the hostile attitude of the local public and the non-availability of an encumbrance-free site. The Madras High Court issued an order directing maintenance of status quo, because of which the work came to a standstill. The Contractor sought return of the bank guarantees. However, the Employer did not agree to the said request and informed the Contractor that the contract was still subsisting. The Contractor invoked the force majeure clause in the contract and requested closure of the contract.

After dismissal of the writ petition by the Madras High Court, the Employer directed the Contractor to re-start the project. Upon refusal by the Contractor, the Employer invoked the bank guarantee and awarded the balance work to a new agency. The disputes between the parties were thereafter referred to arbitration. The arbitral tribunal held that the disturbances at the site could not be termed as “hostilities” or acts of “public enmity” and, therefore, did not qualify as a condition of force majeure. The refusal of the Contractor to resume the work clearly amounted to abandonment of work. The Court held that interpretation of the contract lies predominantly within the domain of the arbitral tribunal.

Authors

RAUTRAY & CO.

Law Firm

Dharmendra Rautray &
Ginny Jetley Rautray

B3/18 Vasant Vihar,
Paschimi Marg,
New Delhi – 110057

Tel: +91.11.46552244 / 46113964
E: mail@rautray.com

Rautray & Co. law firm is a Top Tier ranked firm by Asia Pacific Legal 500 in Dispute Resolution for the years 2023, 2024, 2025 and 2026.