Rautray Advocates & Solicitors
Issue 101June 2026
C.A.N.

Construction Arbitration

Newsletter
RAUTRAY & CO.
Construction Arbitration Law Firm
www.rautray.com

Construction Arbitration — Issue 101

Absence of reasons in arbitral award

Absence of reasons in arbitral award - no analytical linkage between the observations and the ultimate conclusions reached - findings recorded not supported by any cogent reasoning or legal analysis and no meaningful consideration of the pleadings, evidence, or submissions advanced by both parties - mere reproduction or reiteration of the submissions and factual assertions advanced on behalf of the parties, without independent adjudicatory analysis, does not constitute discernible reasoning - award liable to be set aside.

Indian Oil Corporation v. M/s. Metro Builders (Orissa) Pvt. Ltd.

Extension of Time and rescheduling of Milestones

Extension of Time and rescheduling of Milestones - failure to apply for rescheduling - clause in the contract providing that failure to apply for rescheduling would not prevent the authority from rescheduling the milestones - once time was extended, the milestones ought to have been correspondingly rescheduled - Extension of time ordinarily requires corresponding rescheduling of contractual milestones, particularly where delay is not attributable to the Contractor - arbitral tribunal’s finding that withholding of money for non-achievement of milestones was unjustified was a plausible interpretation of the contract and warranted no interference.

Indian Oil Corporation v. M/s. Metro Builders (Orissa) Pvt. Ltd.

Claim for GST and VAT reimbursement

Claim for GST and VAT reimbursement - proof of payment - Contractor failed to prove payment of the alleged additional 3% tax - award of claim towards the alleged 3% GST difference is contrary to law.

Union of India v. Anand and Company

Claim for damages under Section 73 of the Contract Act

Claim for damages under section 73 of the Contract Act - proof of actual loss - unless such proof is impossible a Chartered Accountant's certificate of expenditure alone does not establish compensable loss.

Union of India v. Anand and Company
Indian Oil Corporation v. M/s. Metro Builders (Orissa) Pvt. Ltd.
Delhi High Court — Decided on 2.4.2026

The Employer awarded to the Contractor a construction contract. During execution, the Contractor encountered several hindrances and delays, including delays arising from procurement of imported materials and local supply constraints. The Contractor challenged the levy of price discount by the Employer for delay. The arbitral tribunal allowed the claim of the Contractor and directed refund of the price discount together with interest.

The Court set aside the award concluding that mere reproduction of the Contractor's submissions, and narration of pleadings does not amount to adjudicatory reasoning. There was no logical bridge between evidence and conclusion. The Court held that failure to provide intelligible reasons violates the statutory mandate of section 31(3) of the Arbitration and Conciliation Act, 1996.

The dispute also concerned withholding of money for non-achievement of contractual milestones. The project completion period had been repeatedly extended, the delays were not attributed to the Contractor and the Contractor had in fact sought rescheduling of milestones. Once time was extended, the milestones ought to have been correspondingly rescheduled.

The arbitral tribunal’s finding that the withholding of money for non-achievement of milestones was unjustified was held to be a plausible interpretation of the contract and warranted no interference.

Union of India v. Anand and Company
Delhi High Court — Decided on 4.4.2026

The Employer awarded to the Contractor the contract for construction of 100 Family Quarters (Type-II, III & IV) along with internal water supply, sanitary installation and electrical works for the ITBP 22nd Battalion Campus at Chhawla, New Delhi.

During execution, disputes arose regarding withholding of money for non-achievement of contractual milestones, reimbursement of GST/service tax, payment of the final bill, refund of penalty for delay in completion of the sample flat and damages for prolongation of the contract. The disputes between the parties were referred to arbitration.

The Contractor claimed reimbursement towards an alleged additional 3% tax. The Contractor failed to prove payment of the alleged additional 3% tax and the award of the claim towards the alleged 3% GST difference was held to be contrary to law.

The Contractor also claimed damages under section 73 of the Contract Act. The Court held that proof of actual loss is required and, unless such proof is impossible, a Chartered Accountant's certificate of expenditure alone does not establish compensable loss.

Authors

RAUTRAY & CO.

Law Firm

Dharmendra Rautray &
Ginny Jetley Rautray

B3/18 Vasant Vihar,
Paschimi Marg,
New Delhi – 110057

Tel: +91.11.46552244 / 46113964
E: mail@rautray.com

Rautray & Co. law firm is a Top Tier ranked firm by Asia Pacific Legal 500 in Dispute Resolution for the years 2023, 2024, 2025 and 2026.